Data center construction delays: what holds projects up in 2026

Why data center projects slip in 2026: electrical equipment lead times, power access, local opposition and labor, with what each means for the people building them.

6 min read · Updated November 2026

Written by the DCP team · Reviewed by a commissioning lead with 12 years on live sites · LAST REVIEWED:

Data center construction delays in 2026 come mostly from power and electrical equipment, which CBRE calls the main driver of delays. Medium voltage switchgear can take 40 to 60-plus weeks to arrive, and a building cannot be energized without it. Local opposition and labor shortages add to the risk: Baird counted 25 cancelled projects in 2025, up from six in 2024.

Spending on data centers is at record levels, yet many projects take longer than planned or never start. Construction Dive, citing CBRE, reported that capacity under construction fell nearly 6% year over year in the second half of 2025, even as demand stayed strong.

This guide explains the four things that hold data center projects up, using research firm data and contractors' own words, and what each one means if you work on site.

Part of our guides to data center construction careers.

What is the biggest cause of data center construction delays?

Power and the equipment that delivers it. "Power and electrical equipment is still the main driver of construction delays," CBRE's Gordon Dolven told Construction Dive in March 2026.

Lead times are the problem. Brennan Church of Hut 8 told Construction Dive that medium voltage switchgear is "often at 40 to 60-plus weeks," which at the top end is more than a year. As he put it, a shell can be finished and mechanically roughed in, "but if the gear isn't onsite, you're not energizing."

Why are data center projects being cancelled?

Construction Dive reported in April 2026, citing a Baird research note, that data center cancellations rose from six in 2024 to 25 in 2025. Baird counted at least 188 local opposition groups across 40 states, and construction-ban proposals in more than a dozen states.

"The number one concern we have in the market right now is public sentiment," Rob LoBuono of Gensler said in the same report. Church summed up the risk: "What looks viable on paper usually breaks down on power, permitting or labor, and sometimes all three."

Is there a labor shortage on data center sites?

In many regions, yes. In an ENR report from November 2026, Helix Electric's Casey Long said "labor availability remains constrained." Hunt Electric, which works in 41 of the lower 48 states, said it has enough labor in Minneapolis and St. Paul but elsewhere is "paying premium rates, per diems and incentives to attract and retain workforce."

There is good news for newcomers. Encore Electric's Andy Gordon told ENR: "We have more entry-level candidates looking to start careers in the trades than ever."

How contractors are working around the delays

Contractors are changing how they build. ENR reports that electrical contractors are leaning on prefabrication, modular construction and earlier collaboration. A Lighthouse Electric director wrote in ENR that his teams "get onboarded to data center projects that barely have drawings," and that coordination now happens in shared live models with all the trades at once.

  • Long-lead gear is ordered early, so it can show up before the building is ready for it.
  • More work moves into prefab shops and arrives on site as assemblies.
  • Trades join before the design is finished and bring lead-time knowledge to it.
  • Records and inspections matter more, because late changes have to be tracked cleanly.
Where a data center schedule usually slips
  1. 1

    Power

    Utility capacity secured?

  2. 2

    Permits

    Local approval and opposition.

  3. 3

    Gear

    Switchgear 40 to 60+ weeks.

  4. Labor

    Trades available locally?

Interview questions about schedule pressure

Site and contractor interviews test how you behave when the schedule slips. Three questions to prepare:

The switchgear is late and the schedule is slipping. What can your crew still do safely?

Why they ask
Interviewers want people who keep work moving without cutting corners.
What a scoring answer covers
Name the work that does not depend on the gear, and what must wait.
Model answer
I would check with the superintendent which areas are released, then focus on work that does not need the gear, such as pathways, supports and cable pulls where allowed. Anything that touches energization waits for the equipment, the inspections and the right permits.
Red flag
Offering to skip inspections or hold points to catch up.

You are working from drawings that keep changing. How do you avoid installing the wrong revision?

Why they ask
Early starts mean more revisions, and rework is expensive.
What a scoring answer covers
Check the current revision every time and raise conflicts early.
Model answer
Before I start, I confirm the document number and revision against the current register, not a printout in a truck. If what I see on site does not match, I stop and raise an RFI rather than guessing.
Red flag
Saying you just build from whatever set you were handed.

Why do you want to work on data centers when projects can be delayed or cancelled?

Why they ask
It tests whether you understand the market and still want in.
What a scoring answer covers
Show you know the risks and why the skills carry over.
Model answer
I know some projects slip, mostly over power, gear and permits, but the work that does go ahead is complex and well run. The discipline I learn here, records, inspections and coordination, carries to every project after it.
Red flag
Only mentioning the pay.

The numbers in this guide, and what kind of number each one is

FigureWhat it isSource and status
40 to 60+ weeks Medium voltage switchgear lead time Hut 8 executive via Construction Dive, contractor estimate
Nearly 6% Fall in capacity under construction, H2 2025 CBRE via Construction Dive
6 to 25 Cancelled projects, 2024 to 2025 Baird via Construction Dive, research count
188+ in 40 states Local opposition groups Baird via Construction Dive, research count
41 of 48 Lower 48 states one electrical contractor works in Hunt Electric via ENR

Frequently asked questions

What causes data center construction delays?
Mainly power and electrical equipment. CBRE told Construction Dive that power and electrical equipment are still the main driver of delays, and medium voltage switchgear can take 40 to 60-plus weeks to arrive. Local opposition, permitting and labor shortages add to it.
How many data center projects have been cancelled?
Construction Dive reported, citing a Baird research note, that cancellations rose from six in 2024 to 25 in 2025, with at least 188 local opposition groups across 40 states.
Is there a shortage of electricians for data centers?
In many regions. Electrical contractors told ENR in November 2026 that labor availability remains constrained, and one said it pays premium rates, per diems and incentives outside its home market.

Key takeaways

  • CBRE says power and electrical equipment are still the main driver of data center construction delays.
  • Medium voltage switchgear can take 40 to 60-plus weeks; without it a finished shell cannot be energized.
  • Baird counted 25 cancelled projects in 2025, up from six in 2024, and at least 188 local opposition groups in 40 states.
  • Some electrical contractors pay premium rates, per diems and incentives where labor is short.
  • Prefab, early ordering and earlier trade involvement are how contractors work around the delays.

Sources and review notes

This article uses generalized public guidance and DataCenterPrep's safe-content rules. Actual equipment, procedures, legal requirements, and authorization vary by employer and location.

Generalized, vendor-neutral guidance, not site-specific, legal, or safety advice. Always follow your employer's instructions and official site induction. Last reviewed: July 2026 · DataCenterPrep engineer review.

Next · Be the crew that keeps clean records

Show you can work through schedule pressure the right way

The Contractor & CSA Readiness Kit covers permits, inspection points, handover records and the interview questions site and contractor roles face.

Where you are on the Build path

Build roles are gated at the fence line: site access and safety induction first, interviews only for the supervisory roles.

  1. This page's prep
    GET ON SITE

    Contractor & CSA Readiness Kit

    USD $59

    Walk onto a live construction site ready to be useful: induction, permit-to-work, LOTO, RAMS, confined-space, lift-plan and plant-prestart literacy.

    View this rung
  2. PROVE IT ON PAPER

    CV, LinkedIn & Evidence Kit

    USD $39

    Turn what you know into truthful evidence a screener can act on.

    View this rung
  3. SUPERVISE

    Build Supervisory Interview Module

    USD $99

    Interview prep for the build roles that DO interview: Superintendent, Project Manager, Estimator.

    View this rung
  4. QUALITY GATE

    QA/QC Quality Engineer Prep Pack

    USD $89

    Read and build an ITP, run a non-conformance, assemble a handover record. The quality role nobody prepares you for.

    View this rung
  5. ALL THREE

    Build Interview Bundle

    USD $199 Save $48

    All three Build gates on one receipt: site access, the quality gate, the supervisory interview.

    View this rung

This page's prep is Data Center Contractor & CSA Readiness Kit → the step up from it is Data Center CV, LinkedIn & Evidence Kit ($39). Turn what you know into truthful evidence a screener can act on.

Choosing a certification first? The Certification & Vendor-Course Navigator shows which one to take and in what order, $24.

Moving up into quality? QA/QC is the bridge from Build into the Engineer path: its Commissioning QA interface feeds the Design & Commissioning Prep Pack. Preview the Engineer path

Awareness-level familiarity with site and safety procedures. Not a certification, site authorization, or permit to work. Follow your employer's and site's own procedures and standards (CIBSE Code M · NFPA 70E · OSHA guidance).